HS2 Work Notification: Utility works, Mixbury, March - August 2021

We will be carrying out utility works as part of our work to build the railway.

WPD work paused in September 2020 and will return to site in March 2021 to complete the diversion work. In March 2021 the overhead line works will recommence, the towers will be installed and diverted off the existing towers onto the underground cable section. These works are planned to be completed by August 2021.

Please see our notification for further information

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk.

Posted on 3rd March 2021