HS2 in Bucks & Oxfordshire logoHS2 in Bucks & Oxfordshire

Get project news

Do you want to receive an email when news items are posted?

News on HS2 in Bucks & Oxfordshire

Back to news

HS2 Work Notification: Utility works Turweston, March - August 2021

We will be carrying out utility works as part of our work to build the railway.

WPD paused work in November 2020 and will return to site in March 2021 to complete the diversion works. WPD built all but two high voltage towers in 2020 and left the site ready for work to recommence in 2021. In March 2021 the overhead line works will begin and will be diverted off the existing towers onto the underground cable section. These works are planned to be completed by August 2021.

Please see our notification for further information

If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk.

Posted on 3rd March 2021

by HS2 in Bucks and Ox