HS2 Works Notification: National Grid utility works between Great Missenden and Aylesbury, September 2019 – Autumn 2020

National Grid will be moving and raising the heights of some electricity pylons that the new railway will pass under in four separate locations between Great Missenden and Aylesbury and will also carry out minor routine maintenance work to replace equipment on five pylons in Aylesbury at the same time.

They will create a new access off the A413 so they can reach two pylons near Nash Lee Road and build a new bellmouth and haul road off Bishopstone Road to enable our vehicles, staff, plant and equipment to access pylons west of Aylesbury.

We will need to temporarily close some footpaths and Public Rights of Ways while they are working in the area.

You can find out more detailed information on our works notification sheets and maps , giving you details of locations, times and any diversions.

Posted on 23rd August 2019