The final works required to complete the A413 junction, including road closures on the A413.
The main works will involve:
• Planned closure of the A413 at Bottom House Farm Lane in both directions from the week commencing 1 March 2021.
• Overnight diversions on the A413
• Completion activities for the final road surfacing, traffic light installation and white lining
• Widening the existing lane from Upper Bottom House Farm to the A413
• Excavating holes and using construction machinery
For further information please see our works notification
You might notice some additional traffic on local roads and noise from equipment used for the works, but we will mitigate any environmental impacts including noise and traffic.
If you have a question about HS2 or our works, please contact our HS2 Helpdesk team on 08081 434 434 or email hs2enquiries@hs2.org.uk